Blackout Highlights Business-Continuity Drivers

 
 
By Brian Fonseca  |  Posted 2004-04-09 Email Print this article Print
 
 
 
 
 
 
 

An investigative report issued by the U.S. and Canadian governments surrounding the worst power failure in U.S. history is shedding light on the importance of business-continuity planning through findings that the electric-system catastrophe could have be

An investigative report issued this week by the U.S. and Canadian governments surrounding the worst power failure in U.S. history is shedding light on the importance of business-continuity planning through findings that the electric-system catastrophe could have been prevented. The U.S.-Canada Power System Outage Task Force placed much of the blame for the Aug. 14-15 blackout on FirstEnergy Corp., based in Akron, Ohio. The monstrous power outage crippled parts of Ohio, seven other states and Ontario, cutting off electricity to an estimated 50 million customers as the cascading failure mercilessly sped along transmission lines.
In some parts of the United States, power was not restored for four days. Estimates of total costs of the blackout range between $4 billion and $10 billion.
In its final report, the task force said "inadequate situational awareness" at FirstEnergy in part contributed to the blackouts beginnings in eastern Ohio. Specifically, investigators highlighted factors that served as dominos leading to the collapse. Those factors included faulty software and control-room procedures at FirstEnergy that led to an alarm-system failure, the inability of FirstEnergy to properly recognize and shut off 15,000 megawatts of power to its customers as a contingency measure, and vegetation affecting power lines.
Investigators offered 46 recommendations to prevent another widespread plunge into darkness, spearheaded by a recommendation to make reliability standards mandatory and enforceable with stiff penalties for noncompliance violations. Currently, the private NERC (North American Electric Reliability Council) oversees the voluntary requirements. Next page: FirstEnergy claims problems are industrywide.


 
 
 
 
Brian Fonseca is a senior writer at eWEEK who covers database, data management and storage management software, as well as storage hardware. He works out of eWEEK's Woburn, Mass., office. Prior to joining eWEEK, Brian spent four years at InfoWorld as the publication's security reporter. He also covered services, and systems management. Before becoming an IT journalist, Brian worked as a beat reporter for The Herald News in Fall River, Mass., and cut his teeth in the news business as a sports and news producer for Channel 12-WPRI/Fox 64-WNAC in Providence, RI. Brian holds a B.A. in Communications from the University of Massachusetts Amherst.
 
 
 
 
 
 
 

Submit a Comment

Loading Comments...
 
Manage your Newsletters: Login   Register My Newsletters























 
 
 
 
 
 
 
 
 
 
 
Thanks for your registration, follow us on our social networks to keep up-to-date
Rocket Fuel