Your prospects are sourcing new services at an ever increasing rate, which gives you the opportunity to stand out! In order to seize this opportunity, you need compelling IT services that support core business needs, are high value, drive profits and are cost effective to deliver. Join this eSeminar and learn how to structure and manage services to expand your customer base. Register now, attend live or view
on-demand!
Data Centers Nearing Power-Usage, Cost Crisis (
Page 1 of 2 )
A survey identifies a major issue: old, decommissioned servers that are still running and wasting power.
A new research study on data center capacity and energy efficiency has found that ever-increasing power and cooling costs are affecting the economics of IT more profoundly than many industry observers had thought.
The study, conducted by the Uptime Institute in Santa Fe, N.M., represented the views of 311 enterprise data center managers. The data was recorded over the last two weeks.
Forty-two percent of respondents indicated that their data centers would run out of power capacity within 12 to 24 months if they did no expansion. Twenty-three percent claimed they would run out of power capacity in 24 to 60 months.
Similarly, 39 percent claimed that their data centers would run out of cooling capacity in 12 to 24 months, and 21 percent claimed they would run out of cooling capacity in 24 to 60 months.
"Unless they have unlimited access to money, senior IT executives can no longer ignore [data center] power and cooling costs," Kenneth G. Brill, executive director of the Uptime Institute and director of the research study, told eWEEK. Brill recently keynoted eWEEK's Data Center Summit in New York City.
"We found confirmation for what we call the 'Economic Breakdown of Moore's Law,'" Brill said. "Basically, the increasing cost for power and cooling are fundamentally and almost invisibly changing the economics of IT."
Virtually every respondent to the survey reported they were running out of power and cooling capacity, Brill said, which has resulted in a boom in data center construction and reconstruction.
"All money going into data center construction is coming out of IT's budget," Brill added.
Every 1U [smallest size] server incurs an annual facility cost of about $1,600 per year, Brill said. Of this, about $700 is for electricity. Since the street price for a volume server is in the $3,000 range, the electricity usage itself over four years will exceed the acquisition cost of the server, Brill said.
"This will occur even faster in high utility rate regions like New York City and the northeast," Brill said. "On a total cost of ownership basis, power and cooling costs will exceed the cost of a server in less than two years. This is a radical change from less than eight years ago, when it took 10 to 15 years for site costs to equal server acquisition costs."
Test drive and take home three new products!
Attend the upcoming launch of three powerful new products, take a test drive, meet the teams, and leave with promotional copies of Windows Server® 2008, Microsoft® SQL Server® 2008, and Microsoft Visual Studio® 2008. Register today!>>
Tech-Ed 2008 Microsoft’s premier technical education conference for developers and IT professionals.
June 3-6 & 10-13 | Orlando, FL Register today!
Sponsored by Ziff Davis Enterprise Group
DOWNLOADABLE ROI CALCULATORS & TOOLS FROM BASELINE
Calculate Cost and ROI of Spam, VOIP, RFID, Sarbanes-Oxley and more...