Air Force Losing Way with GPS
With the United States' legacy GPS
satellites progressively failing and the Air Force's efforts to replace them
faltering, the Government Accountability Office says there are serious
questions looming as to whether the government will be able to acquire new
satellites in time to maintain current military, enterprise and civilian GPS
needs without interruption.
In addition to deploying GPS for military
use, the U.S.
government provides GPS service free of
charge and plans to invest more than $5.8 billion over the next five years in GPS
satellites and ground control segments. The Department of Defense provides most
of the funding for the GPS system and the
Air Force is responsible for GPS acquisition
and is in the process of modernizing the GPS.
The U.S.
currently has 31 GPS satellites in orbit,
grouped in an array known as a constellation. The current block upgrade of GPS
satellites has overrun its original estimated cost of $729 million by an
additional $870 million. In addition, the block will be completed three years
late.
"If the Air Force does not meet its schedule goals for development of GPS
IIIA satellites, there will be an increased likelihood that in 2010, as old
satellites begin to fail, the overall GPS
constellation will fall below the number of satellites required to provide the
level of GPS service that the U.S.
government commits to," the GAO said in the GPS report. (PDF)
In addition to predicting that a two-year delay in the program could lead to a
deterioration of the constellation by 2010, the GAO said the delays in the
replacement program might reduce the constellation to 18 satellites before full
recovery in 2020.
In an additional analysis, GAO outlined a scenario in which, if the GPS
block encounters even just a two-year delay, the probability of maintaining a
full service constellation drops precipitously starting in October 2013,
possibly going as low as 10 percent by 2018.
Rep. John Tierney (D-Mass.), the chairman of the Subcommittee on National
Security and Foreign Affairs, blamed the possible lag in the GPS
system upgrade on Department of Defense contracting rules.
"This is not a new problem to DOD procurement. We have another situation
where the contractor-given total system responsibility for the development-could
not execute the job either on time or on budget," Tierney said at a May 7
hearing.
According to the GAO, "No major satellite program undertaken in the past
decade has met its scheduled goals."
Tierney said, "It would seem that GPS
is no exception. What was billed as an effort to streamline the acquisition process
instead resulted in a lack of oversight and control by the Air Force and
Department of Defense. Like the predecessor GPS
block and so many other DOD procurements, the contract is a 'cost plus' type
contract, meaning the government will pick up the tab no matter how expensive
it ends up becoming."
Tierney added, "The reality is that from an acquisition perspective, we
are nearing the 11th hour. The president's fiscal 2010 budget terminates
funding for the primary GPS backup system,
LORAN. That puts a lot of pressure on DOD to ensure GPS
meets all user needs-a precarious position to be in if a gap is looming."
